Photos
• At the top-right, the new 900mm HDPE Outfall has been installed from the main outfall manhole, SMH 275. Top-left is the detailed excavation/mud-slab for the south-east clarifier/bioreactor.
• Next to this, then contractor is placing and compacting 75mm minus imported fill materials as engineered fill for the foundation of what will be the western two of the four clarifier/bioreactors for the CWWTP.
• The center of the picture is the detailed excavation and mud-slab for the bioreactor process gallery; in the lower middle of the picture, the sump for the gallery has been cast (square box).