• Skip to main content
  • Jump to navigation
  • Search

Page Outlines

Loading...

    IE10 and below are not supported.

    Google Chrome Mozilla Firefox

    Contact us for any help on browser support

    You are here:

    • Home
    • Consolidated Wastewater Treatment Plant - COMPLETED

    Photos

    Process Building Construction 2021-10-27
    previous next
    • Left side is the Process Building basement. The grit vortex foundation has been completed, along with the 4-chamber effluent splitter-box where the Process Mains will connect to carry effluent down to the Bioreactor Complex. Far left is the staging/assembly area for the Process Building reinforcing steel. • The Rough-Terrain (RT) Crane is assisting with form removal and installation of reinforcing steel. • In the center of the picture is the Septage Receiving Station (SRS) sump cast in concrete (square recessed concrete area adjacent to the Tower Crane concrete bucket). • The right-side of the picture shows the detailed excavation and mud-slab complete for the Process Building ground-floor, with underground duct-bank for the electrical system stubbed up, as well as numerous sub-floor treatment process piping stubs. All sub-floor piping for the Process Building has been completed in preparation for the placement of ground-floor concrete slab. • Lower right-hand corner is the 900mm HDPE duct from the Process Building to the Odour Control building (large circular stubbed pipe near the skid-steer). • Green tarping has been installed to protect certain elements of the Process Building mud-slab in preparation for the installation of the ground-floor reinforcing steel mat.
    2022-07-19 - CWWTP Outfall In-Shore End.jpg
    2022-07-19 - CWWTP Outfall Off-Shore End.jpg
    2022-07-22_CWWTP_outfall_completion(2).jpg
    2022-07-22_CWWTP_outfall_completion.jpg
    CWWTP_jul-30, 2022.PNG
    plant_site_may-4-2023_graham_photos.JPG
    CWWTP Process Building - May 26, 2022_Page_3.png
    Process Building Construction 2021-10-27
    Outfall Tie-In 2021-10-27
    Bioreactor Complex 2021-10-27
    Tower Crane
    Conceptual Design: Natural Integration Theme
    Outflow
    Current location of the Westview water treatment plant - to be decommissioned
    Current location of the Wildwood lagoon - to be decommissioned
    Current Townsite Wastewater Treatment Plant - to be decommissioned
    Wastewater Treatment Plant Process
    Wastewater to water - Powell River's current wastewater treatment